• Purchase Order changes: (see screenshots below)
  1. Added two fields to PODetails: ETA1 and ETA2
  2. When creating a new PO, ETA1 will default to the order due date + dock to stock days in calendar days.
  3. ETA1 can be changed before the order is saved for the first time.
  4. ETA2 will be set to ETA1 when the order is saved for the first time.
  5. When editing an existing order, ETA1 will be disabled and ETA2 can be changed.

Bulk update existing purchase orders – Updated fields ETA1 and ETA2 to order due date + dock to stock days in calendar days.


  • MRP changes:
  1. Changed PO item due date calculation. Previously the MRP calculated an item’s due date from the orders due date and added the item’s dock to stock days in working days. Changed it to use the ETA2 date field.